Where a late application for building warrant is made, or a completion certificate is submitted and there was no warrant obtained when there should have been, the fee is increased to cover the increased difficulty the verifier will have in establishing whether work that is already underway or completed complies with the plans, specifications and other information provided.
The resulting fees are:
Application Type | Fee (from April 2024) | Fee (from April 2025) |
---|---|---|
Application for late building warrant, i.e. where work is already started: | ||
|
Fee is 200% of the fee in Amendment to Warrant table. | Fee is 200% of the fee in Amendment to Warrant table. |
|
£150 | £300 |
Submission of a completion certificate where no warrant was obtained for: | ||
|
Fee is 300% of the fee in Amendment to Warrant table. | Fee is 300% of the fee in Amendment to Warrant table. |
|
£400 | £500 |